Question: draw and Compute the expected time for each activity and the expected duration for each path: The expected time ( TE ) for each activity

draw and Compute the expected time for each activity and the expected duration for each path:
The expected time (TE) for each activity is calculated using the following formula:
TE =(a +4m + b)/6
Where:
a = Optimistic time
m = Most likely time
b = Pessimistic time
The expected duration for each path is the sum of the expected times for the activities along that path.
Activity Expected Time (TE)
A: TE =(3+4(6)+8)/6=6 weeks
B: TE =(2+4(4)+4)/6=4 weeks
C: TE =(1+4(2)+3)/6=2 weeks
D: TE =(6+4(7)+8)/6=7 weeks
E: TE =(2+4(4)+6)/6=4 weeks
F: TE =(6+4(10)+24)/6=12 weeks
G: TE =(1+4(2)+4)/6=2.33 weeks
H: TE =(3+4(6)+9)/6=6 weeks
I: TE =(10+4(11)+12)/6=11 weeks
J: TE =(14+4(16)+20)/6=16.67 weeks
K: TE =(2+4(8)+10)/6=7.33 weeks
Possible paths and their expected durations:
Path 1:
weeks
Path 2:
weeks
Path 3:
weeks
Path 4:
weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!