Question: draw and Compute the expected time for each activity and the expected duration for each path: The expected time ( TE ) for each activity
draw and Compute the expected time for each activity and the expected duration for each path:
The expected time TE for each activity is calculated using the following formula:
TE a m b
Where:
a Optimistic time
m Most likely time
b Pessimistic time
The expected duration for each path is the sum of the expected times for the activities along that path.
Activity Expected Time TE
A: TE weeks
B: TE weeks
C: TE weeks
D: TE weeks
E: TE weeks
F: TE weeks
G: TE weeks
H: TE weeks
I: TE weeks
J: TE weeks
K: TE weeks
Possible paths and their expected durations:
Path :
weeks
Path :
weeks
Path :
weeks
Path :
weeks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
