Question: Draw network diagram. Define the project duration, project critical path and floats for non-critical activities based on the data presented in the Table 1. Table

Draw network diagram. Define the project duration, project critical path and floats for non-critical activities based on the data presented in the Table 1.

Table 1

Project activities characteristics

Activity Code

Predecessor

Duration, weeks

A

-

3

B

-

4

C

A, B

6

D

A

4

E

B

5

K

C

3

L

D, E

4

M

B, E

7