Question: Draw network diagram. Define the project duration, project critical path and floats for non-critical activities based on the data presented in the Table 1. Table
Draw network diagram. Define the project duration, project critical path and floats for non-critical activities based on the data presented in the Table 1.
Table 1
Project activities characteristics
| Activity Code | Predecessor | Duration, weeks | |
| A | - | 3 |
|
| B | - | 4 |
|
| C | A, B | 6 |
|
| D | A | 4 |
|
| E | B | 5 |
|
| K | C | 3 |
|
| L | D, E | 4 |
|
| M | B, E | 7 |
|