Question: Draw PERT Chart with timeing Activity Predecessor activity Optimistic time (a) Likely time (m) Pessimistic time (b) Expected Time T =(a+4m+b)/6 A ---- 1 2

Draw PERT Chart with timeing

Activity

Predecessor activity

Optimistic time

(a)

Likely time

(m)

Pessimistic time

(b)

Expected Time

T =(a+4m+b)/6

A

----

1

2

4

B

----

3

3.5

4

C

----

10

12

13

D

----

4

5

7

E

----

2

4

5

F

A

6

7

8

G

B

2

4

5.5

H

C

5

7.7

9

I

C

9.9

10

12

J

C

2

4

5

K

D

2

4

6

L

E

2

4

6

M

F,G,H

5

6

6.5

N

J,K,L

1

1.1

2

O

I,M

5

7

8

P

N

5

7

9

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!