Question: PERT Problem Analyze the same problem with probabilistic activity times given. Activity Immediate Predecessors Most Optimistic Time Most Likely Time Most Pessimistic Time Expected Time
PERT Problem
Analyze the same problem with probabilistic activity times given.
| Activity | Immediate Predecessors | Most Optimistic Time | Most Likely Time | Most Pessimistic Time | Expected Time (ET) | Variance |
| A | 2 | 3 | 6 | 3.333 | .444 | |
| B | A | 3 | 4 | 5 | 4.000 | .111 |
| C | B | 1 | 2 | 4 | 2.167 | .250 |
| D | B | 3 | 5 | 6 | 4.833 | .250 |
| E | C | 3 | 4 | 5 | 4.000 | .111 |
| F | D | 3 | 3 | 4 | 3.167 | .028 |
| G | E,F | 1 | 2 | 3 | 2.000 | .111 |
Step 3. Find the probability of a scheduled completion date of less than 17 days. a. Sketch out the project mean and project standard deviation assuming a normal distribution with mean and standard deviation found above. Remember the standard deviation is the square root of the variance! _____________________________________________________________
b. Now, find the z value for a scheduled completion date of day 17 on the critical path using the formula: Using the z value, a probability value can be found. __________