Question: PERT Problem Analyze the same problem with probabilistic activity times given. Activity Immediate Predecessors Most Optimistic Time Most Likely Time Most Pessimistic Time Expected Time

PERT Problem

Analyze the same problem with probabilistic activity times given.

Activity

Immediate Predecessors

Most Optimistic Time

Most Likely Time

Most Pessimistic Time

Expected Time (ET)

Variance

A

2

3

6

3.333

.444

B

A

3

4

5

4.000

.111

C

B

1

2

4

2.167

.250

D

B

3

5

6

4.833

.250

E

C

3

4

5

4.000

.111

F

D

3

3

4

3.167

.028

G

E,F

1

2

3

2.000

.111

Step 3. Find the probability of a scheduled completion date of less than 17 days. a. Sketch out the project mean and project standard deviation assuming a normal distribution with mean and standard deviation found above. Remember the standard deviation is the square root of the variance! _____________________________________________________________

b. Now, find the z value for a scheduled completion date of day 17 on the critical path using the formula: Using the z value, a probability value can be found. __________

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!