Question: PERT Problem Analyze the same problem with probabilistic activity times given. Activity Immediate Predecessors Most Optimistic Time Most Likely Time Most Pessimistic Time Expected Time

PERT Problem
Analyze the same problem with probabilistic activity times given.
Activity Immediate Predecessors Most Optimistic Time Most Likely Time Most Pessimistic Time Expected Time (ET) Variance
A 236
B A 345
C B 124
D B 356
E C 345
F D 334
G E,F 123
Step 1. Calculate the expected time for each activity.
Step 2. Identify the different paths in the network and total activity time on path.
(Use the expected times of each activity for this calculation).
Path 1: ________ Time: _________
Path 2: ________ Time: _________
Step 3. Identify the critical path(s) on the network. The critical path is the one having the longest total activity times AND also has no slack.
Critical Path: _________ Total Time: _______

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!