Question: Draw the activity network. What is the critical path? How long does the project take? What is the latest start time for activity C? Critical

Draw the activity network.

What is the critical path?

How long does the project take?

What is the latest start time for activity C?

Critical path Activity Duration Preceeding activity A 3 A 4 7 A

Critical path Activity Duration Preceeding activity A 3 A 4 7 A 14 D F 6 D 10 8. E,F 2 G,H