Question: Calculate the expected time for each activity? Calculate variance for each activity? What is the critical path? What is the expected total time for the

Calculate the expected time for each activity?

Calculate variance for each activity?

What is the critical path?

What is the expected total time for the project?

What is the standard deviation for the critical path?

What is the probability that the project is completed in 34 days?

PERT Activity Preceeding activity Most Optimistic Pessimistic Expected Variance likely time time

PERT Activity Preceeding activity Most Optimistic Pessimistic Expected Variance likely time time time time A 3 4 B A. 4 11 4 B A 10 14 D 12 20 6. 10 10 15 E,F 10 G,H

Step by Step Solution

3.33 Rating (165 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Excel file Icon

604ef288e5a85_734831.xlsx

300 KBs Excel File

Students Have Also Explored These Related Corporate Finance Questions!