Question: Calculate the expected time for each activity? Calculate variance for each activity? What is the critical path? What is the expected total time for the
Calculate the expected time for each activity?
Calculate variance for each activity?
What is the critical path?
What is the expected total time for the project?
What is the standard deviation for the critical path?
What is the probability that the project is completed in 34 days?
PERT Activity Preceeding activity Most Optimistic Pessimistic Expected Variance likely time time time time A 3 4 B A. 4 11 4 B A 10 14 D 12 20 6. 10 10 15 E,F 10 G,H
Step by Step Solution
3.33 Rating (165 Votes )
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
604ef288e5a85_734831.xlsx
300 KBs Excel File