Question: Draw the bar chart for the given project & determine the project total duration. Activity Duration IPA Type Lag A 5 B 7 A SS

Draw the bar chart for the given project & determine the project total duration.

Draw the bar chart for the given project &

Activity Duration IPA Type Lag A 5 B 7 A SS C 8 D 10 ASS, FFSS(3) E 4 B FF 2 F 16 C,DI G 2 E,F