Question: Draw the bar chart for the given project & determine the project total duration. Activity Duration IPA Type Lag A 5 B 7 A SS
Draw the bar chart for the given project & determine the project total duration.

Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock