Question: Draw the Network Diagram . Label each activity with its name and duration using the durations in the Estimate column of the table. Activity Predecessor
Draw the Network Diagram. Label each activity with its name and duration using the durations in the Estimate column of the table.
| Activity | Predecessor | Estimate (Weeks) |
| Start | ---- | ---- |
| A | Start | 9 |
| B | A | 7 |
| C | A | 3 |
| D | B | 6 |
| E | B | 9 |
| F | C | 4 |
| G | E,F | 6 |
| H | D | 5 |
| I | G,H | 3 |
| END | I | --- |