Use the precedence table below to answer the following questions:
a) Given the activities, predecessors, and durations displayed in the precedence table, draw a network diagram. (5 marks)
b) Identify all network diagram pathways and their durations. (6 marks)
c) Identify the critical path(s).(2 marks)
d) Provide the definition for "critical path" (2 marks)
e) How long will it take to complete the project? (1 mark)
f) What is the float (slack) time for activity D?(1 mark)
g) What is the float (slack) time for activity A?(1 mark)
h) What is the float (slack) time for activity G?(1 mark)
i) What is the float (slack) time for activity F?(1 mark)
Activity
Predecessor Activity
Duration in Days
A
None
3
B
J
2
C
H
3
D
None
1
E
D & G
2
F
L & E
4
G
None
3
H
A
3
I
B & M
5
J
None
5
K
C
4
L
A
6
M
G
2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!