Question: Draw the network diagram manually on paper, answer questions on the same page, take a picture of your work and upload your file / s
Draw the network diagram manually on paper, answer questions on the same page, take a picture of your work and upload your filesIf you encounter uploading challenges during the actual midterm exam, you may also email your work to the course instructor within the allotted exam time.
Use the precedence table below to answer the following questions:
a Given the activities, predecessors, and durations displayed in the precedence table, draw a network diagram. marks
b Identify all network diagram pathways and their durations. marks
c Identify the critical paths marks
d Provide the definition for "critical path" marks
e How long will it take to complete the project? mark
f What is the float slack time for activity D mark
g What is the float slack time for activity A mark
h What is the float slack time for activity G mark
i What is the float slack time for activity F mark
Activity
Predecessor Activity
Duration in Days
A
None
B
J
C
H
D
None
E
D & G
F
L & E
G
None
H
A
I
B & M
J
None
K
C
L
A
M
G
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock