Question: Draw the node diagram and perform CPM computations ( forward pass, backward pass and total float ) . Highlight the critical path. ( IPA =

Draw the node diagram and perform CPM computations (forward pass, backward pass and total float). Highlight the critical path. (IPA = immediate Activity Predecessor)
\table[[Activity,IPA,Duration,Activity,IPA,Duration],[A,-,2,H,D,9],[B,A,7,I,F, G,12],[C,A,10,J,F,5],[D,A,4,K,E, J,5],[E,B,6,L,G, H,6],[F,B, C,5,M,F, H,4],[G,C, D,8,N,I, K, L, M,3]]
 Draw the node diagram and perform CPM computations (forward pass, backward

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!