Question: Draw the node diagram and perform CPM computations ( forward pass, backward pass and total float ) . Highlight the critical path. ( IPA =

Draw the node diagram and perform CPM computations (forward pass, backward pass and total float). Highlight the critical path. (IPA = immediate Activity Predecessor)
\table[[Activity,IPA,Lag,Duration,Activity,IPA,Lag,Duration],[A,-,,2,G,C,,5],[B,A,2,5,H,D, E,,10],[C,A,,6,,F,2,],[D,B,,6,I,E, F, G,,8],[E,B,3,7,J,D,,7],[F,B, C,,4,K,H, J,,1],[,,,,,I,1,]]