Question: DRAW THE PROJECT COST-DURATION GRAPH. SHOW YOUR WORK LEADING TO THE CONSTRUCTION OF THE GRAPH Activity Immediate Predecessor a m b 8.5 B A A

DRAW THE PROJECT COST-DURATION GRAPH. SHOW YOUR
DRAW THE PROJECT COST-DURATION GRAPH. SHOW YOUR WORK LEADING TO THE CONSTRUCTION OF THE GRAPH Activity Immediate Predecessor a m b 8.5 B A A B DE 1.5 2 2 1 2.5 2 2.5 3 2.5 3.5 1 D E F Max Reduction/ Crash Time 1 1 2 2 1 0 6 10 7 7.5 1.5 Normal Cost (5) 150 100 200 200 200 150 Cost/ Time (Slope) 50 100 60 60 70 0 0.5 Duration 12 11 10 9 8 Indirect Costs 1600 1500 1400 1300 1200