Drawn a handwritten AON (activity on node) network diagram representing the project. Show ES, EF, LS, LF.
Fantastic news! We've Found the answer you've been seeking!
Question:
- Drawn a handwritten AON (activity on node) network diagram representing the project. Show ES, EF, LS, LF.
- What is the project duration?
- What is the critical path?
b. Write down all the paths of the network diagram and write down how long they each are.
c. What is the shortest possible time it will take to complete this project?
ID | Description | Predecessor | Time (Days) |
A | Pour foundation | None | 3 |
B | Erect frame | A | 4 |
C | Roof | B | 4 |
D | Doors | B | 1 |
E | Windows | B | 1 |
F | Electrical | B | 3 |
G | Rough in Frame | C, D, E, F | 2 |
H | Door Opener | E, F | 1 |
I | Paint | G, H | 2 |
J | Clean up | I | 1 |