Question: Duration Activity B D E Dependency None A None 2 1 3 B, C CD E F,G H. Finish to Start Lag 3 from 1

Duration Activity B D E Dependency None A None 2
Duration Activity B D E Dependency None A None 2 1 3 B, C CD E F,G H. Finish to Start Lag 3 from 1 B E H F J D G Legend ES ID EF SL SL LS DurLF Critical Path(s) 8b. (2 Points) What will happen to the length project if task C takes one day longer than planned? Does the critical path(s) change? How? 8c (2 Points) What will happen to the length of the project if task F takes one day longer than planned? Does the critical path(s) change? How