Question: Duration Activity Predecessor (weeks) a none 12 b none 5 c ab 7 d 2 . b e 8 f e 9 S d 5

Duration Activity Predecessor (weeks) a none 12 b
Duration Activity Predecessor (weeks) a none 12 b none 5 c ab 7 d 2 . b e 8 f e 9 S d 5 fig 8 Your firm is implementing a balanced Scorecard. As the project manager, you need to make sure the project is completed on time and on-budget. The table below lists the steps that need to be complete. What is the length of the project? 34 29 30 32