Question: Durations Immediate Activity (weeks) Predecessor ---------- ----------- -------------- A 10 - B 14 - C 3 - D 14 A E 15 B F 11
Durations Immediate
Activity (weeks) Predecessor
---------- ----------- --------------
A 10 -
B 14 -
C 3 -
D 14 A
E 15 B
F 11 B
G 8 C
H 13 D
I 6 B
J 13 F
K 1 G
L 4 G
M 7 K, L
N 6 H, M
O 10 I, N
a) Draw the AON Network for this project
b) Draw the AOA network for this project.
c) Determine the project durations
d) Identify Critical paths
e) Determine the slack time for each activity.