Question: During a very mild fall, Dave and Pat entered into a valid contract for Dave to build an in - ground swimming pool on Pat

During a very mild fall, Dave and Pat entered into a valid contract for Dave to build an in-ground swimming pool on Pats property. About one week before the agreed start date, the weather suddenly changes, below zero temperatures freeze the ground solid, and an early blizzard shuts down the roads and delays the delivery of necessary supplies. Dave notifies Pat that because of the unexpected bad weather, it is not possible for him to install her in-ground pool until spring. Which of the following statements is true?
Question 3 options:
1)
Daves conduct is an anticipatory breach of his contract with Pat as of the date the pool was scheduled to be completed.
2)
Dave is likely to be able to raise the defense of impossibility, excusing him from not completing the contract as drafted.
3)
Daves conduct is an anticipatory breach of his contract with Pat as of the date he notifies Pat he will not install her pool until the spring.
4)
Daves conduct is not a breach of his contract with Pat because he had not yet started the work.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!