Question: During project executing, a team member comes to project manager because he is not sure of what work needs to be accomplished on the project.
During project executing, a team member comes to project manager because he is not sure of what work needs to be accomplished on the project. Which of the following documents contains the detailed description of work packages?
Select one:
a. WBS dictionary.
b. Scope management plan
c. Project scope statement.
d. Activity List.