Question: During project executing, a team member comes to project manager because he is not sure of what work needs to be accomplished on the project.
During project executing, a team member comes to project manager because he is not sure of what work needs to be accomplished on the project. Which of the following documents contains the detailed description of work packages?
A. * WBS dictionary.
B. Activity List.
C. Project scope statement.
D. Scope management plan.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
