Question: E Start Finish B D G Activity A B C D E F G Time 3 2 5 5 6 2 2 The crashing data

E Start Finish B D G Activity A B C D E F G Time

E Start Finish B D G Activity A B C D E F G Time 3 2 5 5 6 2 2 The crashing data for this project we as follows: Activity A B c D E F Time (days) Normal Crash 3 2 2 1 5 3 5 6 2 1 2 1 Cost (5) Normal Crash 800 1400 1200 1900 2000 2800 1500 2300 1800 2800 600 1000 500 1000 Assume that management desires a 12-day project completion time. a. Formulate a linear programming model that can be used to assist with the crashing decisions. b. What activities should be crashed? c. What is the total project cost for the 12-day completion time