Question: Earned Value is a way to track project performance against a baseline. One way to use earned value is as a snapshot view of the
Earned Value is a way to track project performance against a baseline. One way to use earned value is as a snapshot view of the current status when data was last gathered. Which of the following terms are associated with earned value as a current status?
To-Complete Performance Index (TCPI)
Planned Value (PV)
Schedule Variance (SV)
Cost Variance (CV)
All of the above B, C, & D only