Question: Earned Value Management Example 1: Earned Value Management You are the Project Manager on a project. The project is expected to be completed in 10

Earned Value Management Example 1: Earned Value
Earned Value Management Example 1: Earned Value Management You are the Project Manager on a project. The project is expected to be completed in 10 months at planned cost of $1,000 per month. After 6 months the project is 55% completed. The planned value after 6 month is $6,000, and the actual certified expenditure after 6 month is $6,750. Determine the status of the project after 6 month. PV cumulative (S-Curve Cumulative Cost Project Duration SO 10 months Time

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!