Question: Earned value problem A project has 4 tasks, namely, A , B , C , and D . A , B , and C have
Earned value problem
A project has tasks, namely, A B C and D A B and C have no predecessors. C is a predecessor to D As per the status date, A and B should have been completed C should have been completed Baseline cost for these task are: and Actual progress went as: finished at actual cost of ; at Actual cost of ; at actual cost of Calculate CV SVI I baseline project duration, budget at completion, estimate at completion, and the new time estimate to complete the project. How has project done so far? The baseline estimate for project completion time is days.
Planned value
Actual cost
Earned value
I
I
BAC
EAC
Estimate to complete
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
