Question: A project has 4 tasks, namely, A , B , C , and D . The baseline estimate for project completion time is 2 0
A project has tasks, namely, A B C and D
The baseline estimate for project completion time is days.
A B and C have no predecessors.
C is a predecessor to D
As per the status date:
A and B should have been completed
C should have been completed
Baseline cost for these tasks are: A B C and D
Actual progress went as:
A finished at actual cost of ;
B at Actual cost of ;
C at actual cost of
Calculate PV EV AC CV SV CPI, SPI, baseline project duration, budget at completion,
estimate at completion, and the new time estimate to complete the project. How has project
done so far?