Question: A project has 4 tasks, namely, A , B , C , and D . The baseline estimate for project completion time is 2 0
A project has tasks, namely, A B C and D
The baseline estimate for project completion time is days.
A B and have no predecessors.
is a predecessor to
As per the status date:
A and B should have been completed
C should have been completed
Baseline cost for these tasks are: and
Actual progress went as:
finished at actual cost of ;
at Actual cost of ;
at actual cost of
Calculate PV EV AC CV SV CPI, SPI, baseline project duration, budget at co estimate at completion, and the new time estimate to complete the project done so far?