Question: eBook Lead Time completed, the operator moves the assembled boards to the final assembly area. This move takes 1 0 minutes to complete. time between

eBook
Lead Time completed, the operator moves the assembled boards to the final assembly area. This move takes 10 minutes to complete. time between these two operations. Packaging and labeling requires 10 minutes per unit.
Required: percentages to one decimal place. Categorize the non-value-added time into wait and move time.
Value-added lead time min.
Non-value-added lead time:
Wait time lead time
Move time lead time min
Total non-value-added lead time
Total lead time
Value-added ratio (as a percent)
2. Move time in this process could best be reduced by:
a. Doing nothing.
Previous
Next
 eBook Lead Time completed, the operator moves the assembled boards to

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock