Question: Project Scheduling Problem The Project Scheduling Problem tab of the Exam 3 Question Parameters workbook displays the Activity-On-Node (AON) diagram for a project network. Activity


Project Scheduling Problem The Project Scheduling Problem tab of the Exam 3 Question Parameters workbook displays the Activity-On-Node (AON) diagram for a project network. Activity times (in weeks) are shown in the table to the left of the AON diagram. You should: - Enter the "Immediate Predecessors" information into cells B4B11 - Compute and enter the ES, EF, LS, LF, and Slack times for each activity into columns D through H as indicated - Answer the following - How long will the project take? (Enter value) - What is the critical path