Question: 17. The Project Scheduling Problem tab of the Question Parameters workbook displays the Activity-On-Node (AON) diagram for a project network. Activity times (in weeks) are

17. The Project Scheduling Problem tab of the Question Parameters workbook displays the Activity-On-Node (AON) diagram for a project network. Activity times (in weeks) are shown in the table to the left of the AON diagram. You should:
- Enter the "Immediate Predecessors" information into cells B4-B11
- Compute and enter the ES, EF, LS, LF, and Slack times for each activity into columns D through H as indicated
- Answer the following
- How long will the project take? (Enter value)
- What is the critical path?
18. For the project from the question above, what is the impact on total project duration if Activity C is delayed by 1 period - that is, it took 1 period longer than originally planned? Explain.
19. For the project from the question above, what is the impact on total project duration if Activity D is shortened by 1 period? Explain.
Project Scheduling Problem Activity On Node Diagram Immediate Predecessors Time (Weeks) ES EF LS LF Slack Activity A B E none B A A D tooStep by Step Solution