Question: The Project Scheduling Problem tab of the Parameters workbook displays the Activity-On-Node (AON) diagram for a project network. Activity times (in weeks) are shown in

The Project Scheduling Problem tab of the

The Project Scheduling Problem tab of the

The Project Scheduling Problem tab of the Parameters workbook displays the Activity-On-Node (AON) diagram for a project network. Activity times (in weeks) are shown in the table to the left of the AON diagram. You should:

  • Enter the "Immediate Predecessors" information into cells B4-B11
  • Compute and enter the ES, EF, LS, LF, and Slack times for each activity into columns D through H as indicated
  • Answer the following
    • How long will the project take? (Enter value)
    • What is the critical path?

Project Scheduling Problem Immediate Predecessors Time (Weeks) 4 ES EF LS LF Activity A Slack none A 3 A 8 10 - I 10 14 B,C CE D F,G 5 7 Activity On Node Diagram B E A C F H D G

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!