Question: estion 2 points (CH 22 A project was estimated to cost AED 1.5M and scheduled to last for 6 months. Alter three months, what would

estion 2 points (CH 22 A project was estimated to
estion 2 points (CH 22 A project was estimated to cost AED 1.5M and scheduled to last for 6 months. Alter three months, what would be the Schedule Variance gran the following urned value analysis in ALO EV - AED 650.000, PV - AED 750,000 AC - AED 800.000 - 100.000 b. 100.000 50.000 d 50,000