Question: ETW Inc. has released a request for quotation (RFQ) to a group of preferred suppliers for its existing project, ProjectSquid. You have received this RFQ

ETW Inc. has released a request for quotation (RFQ) to a group of preferred suppliers for its existing project, ProjectSquid. You have received this RFQ where the project duration must be 39 days maximum. Your department has planned out the project activities and provided you with the relevant information, as shown in Table IA. Activity durations are for the normal situation, and options for crashing are listed.

ETW Inc. has released a request for quotation (RFQ) to a groupof preferred suppliers for its existing project, ProjectSquid. You have received this

Table la: Project Data Normal Project Cost: RM12,510.00 Activity Duration (Days) Predecessor Possible Max Crash (Day) Crash Slope (RM/Day) A 12 4 180 B 14 N/A C 10 N/A O 16 A 6 140 E 8 A N/A F 14 C N/A G 22 B, E, F 11 180 H 18 C N/A NOT USED L 18 D LO 150 K 14 H 5 80Qla. Draw a complete Arrow-to-Node (AON) network diagram and fill in Table 1B ES EF SL Activity LS Days LF

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!