Question: Evaluate the connected paths through the diagram to determine the expected project completion time. ( Round your answer to 2 decimal places, the tolerance is

Use the network diagram and the following project

Use the network diagram and the following project data. Network diagram B  

Evaluate the connected paths through the diagram to determine the expected project completion time. (Round your answer to 2 decimal places, the tolerance is +/-0.04.)

Expected project completion time = _______ weeks.

Use the network diagram and the following project data. Network diagram B F H E G Optimistic Time Most Likely Time Pessimistic Time Activity Estimate(weeks)Estimates (weeks)Estimates (weeks) A 7 11 11 B 4 10 16 C 4 4 7 7 11 E 3 8 13 F 5 8 9. 4 7 11 H 3 3.

Step by Step Solution

3.45 Rating (152 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To determine the expected project completion time we need to evaluate the connected paths through th... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!