Question: Using the information given and expected project completion time from Problem 13(c), (a) Calculate the probability of completing the project in 36 weeks. (b) Calculate
Using the information given and expected project completion time from Problem 13(c),
(a) Calculate the probability of completing the project in 36 weeks.
(b) Calculate the probability of completing the project in 40 weeks.
Step by Step Solution
3.40 Rating (163 Votes )
There are 3 Steps involved in it
a Pproject 36 Pcritical pat... View full answer