Question: Example 6 : Find the critical path for the following project table [ [ Activity , Description,Duration,Pred. ] , [ A , Evaluate current

Example 6: Find the critical path for the following project
\table[[Activity,Description,Duration,Pred.],[A,Evaluate current technology platform,2,None],[B,Define user requirements,5,A],[C,Design Web page layouts,4,B],[D,Set-up Server,3,B],[E,Estimate Web traffic,1,B],[F,Test Web pages and links,4,C,D],[G,Move web pages to production environment,3,D,E],[H,Write announcement of intranet for corp. newsletter,2,F,G],[I,Train users,5,G],[J,Write report to management,1,H,I]]