Question: Example: One worker Operating two semi - automatic lathes. The cycle consists of Load M / C ( 2 min ) , Machine part (
Example:
One worker Operating two semiautomatic lathes. The cycle consists of Load MC min Machine part minthe machine stops automatically at the end of cut and unloaded machine min The two machines are alike and each completes the machining operation and stops automatically
Construct a workermachine activity chart. The chart is to show the worker starting the machines in the morning with both machines empty and continues until each machine completes two cycles, ie it has machines two pieces. The chart should have one column for the worker and a column each for machine and machine
Estimate the utilization of the worker and the machines.