Question: Exercise 1 1 | An engineer draws up an activity network of 8 activities, assigning the most likely time in weeks for finish in each

Exercise 11|
An engineer draws up an activity network of 8 activities, assigning the most likely time in weeks for finish in each task, as shown in Figure P10.11:
a. Compute the ES, EF, LS, LF, and TF times for the various tasks.
b. What is the critical path and the most likely time the project will be completed?
 Exercise 11| An engineer draws up an activity network of 8