Exercise 2of2
For the network below, calculate for each task, BCWP,BCWS, ACWP, CV,SV, CPI, SPI.
Calculate these numbers for the entire project as well.
Project is16 days old--16 business days have transpired.
Fill out the table below:
Project is16 days old--16 business days have transpired.
Calculate the following:
BAC =
TAC =
EAC =
ETAC =
Comments on the status of your project:
Duration of the critical path is30.