Question: Exercise 3 table [ [ Activity , Predecessors,Duration ( days ) ] , [ A - Select office site,None, 3 ] , [ B

Exercise 3
\table[[Activity,Predecessors,Duration(days)],[A - Select office site,None,3],[B - Create org. and financial plan,None,5],[C - Determine personnel requirements,B,3],[D - Design facility,A, C,4],[E - Construct interior,D,8],[F - Select personnel to move,A, C,2],[G - Hire new employees,F,4],[H - Move records, key personnel, etc,F,2],[I - Train new personnel,E, G, H,3]]
Requirements:
Draw network diagrams for the above exercises.
Determine the critical path.
Calculate the total float(slack) and free float(slack).
 Exercise 3 \table[[Activity,Predecessors,Duration(days)],[A - Select office site,None,3],[B - Create org. and

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!