Question: Exercise: Scheduling in MSProject Complete this exercise in MSProject. Assume a start date ofJune 1 of the current year and a normal 5- day work

Exercise: Scheduling in MSProject Complete this exercise in MSProject. Assume a start date ofJune 1 of the current year and a normal 5- day work week. Submit both your MSProject file and your answers to the questions below. Consider a project that consists of8 tasks with predecessors and task estimates as shown: 1) What is the critical path and what is the expected time to complete the project? 2) If you want to shorten the project to 25 days, which tasks could you \"crash\" to do that? Assume you can shorten any task by up to 3 days at a cost of SlOO/day
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts