Question: Exercise: Scheduling in MSProject Complete this exercise in MSProject. Assume a start date of June 1 of the current year and a normal 5- day

Exercise: Scheduling in MSProject Complete this exercise in MSProject. Assume a start date of June 1 of the current year and a normal 5- day work week Submit both your MSProject file and your answers to the questions below. Considera project that consists of B tasks with predecessors and task estimates as shown: Predecessor Task A B Duration 2 4 8 D E F 8 B,C D D E . 6 3 H 6 1) What is the critical path and what is the expected time to complete the project? 2) If you want to shorten the project to 25 days, which tasks could you 'crash to do that? Assume you can shorten any task byup to 3 days at a cost of $100/day