Question: f 3 . 1 3 . The following represent activities in Marc Masoud s Construction Company project Activity Immediate Predecessor ( s ) Time (
f The following represent activities in Marc Masouds Construction Company project
Activity Immediate
Predecessors
Time
weeks
A None
B None
C A
D B
E B
F C E
G D
H F G
a Drawe the network to represent his situation.
b What activities are on the critical path? Please show your work.
c What is the length of the critical path? Please show your work