Question: Felicity Inc has planned a simple project with four tasks. The task information for the project is shown below: Task Estimated Duration Immediate Predecessors A

Felicity Inc has planned a simple project with four tasks. The task information for the project is shown below: Task Estimated Duration Immediate Predecessors A 10 days None B 7 days A C 4 days A D 8 days B,C Does any task have slack? If so, how much