Question: FF , SF , SS , SF * are logical relationships used in which of the following? ( * FF - Finish to Finish, SF

FF, SF, SS, SF* are logical relationships used in which of the following?
(*FF - Finish to Finish, SF - Start to Finish, SS - Start to Start, SF - Start to Finish)
Group of answer choices
Scope Determination
Project Estimation
Precedence Diagramming Method
ADR

Step by Step Solution