Question: Figure 1 below shows a project WBS with cost apportioned by percent. The total project cost is estimated to be ( $ 2

Figure 1 below shows a project WBS with cost apportioned by percent. The total project cost is estimated to be \(\$ 2,800,000\). What are the estimated costs for the following deliverables: Definition, Fabrication, Assembly and CPU/Software?
Figure 1: WBS of project under consideration
 Figure 1 below shows a project WBS with cost apportioned by

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock