Question: Figure to accompany Table 2.1 B D A 2 E 3 C 3 F Table 21 ACTIVITY A B D E F G SLACK 0

Figure to accompany Table 2.1 B D A 2 E 3 C 3 F
Figure to accompany Table 2.1 B D A 2 E 3 C 3 F Table 21 ACTIVITY A B D E F G SLACK 0 1 0 ACTIVITY EARLIEST EARLIEST LATEST TIME START FINISH START 2 0 0 1 2 3 3 3 2 5 2 7 3 10 4 3 5 8 5 11 4 11 15 11 LATEST FINISH 2 4 5 11 11 11 15 | 0 Refer to the Figure to accompany Table 2.1. Which one of the following is the critical path? (CSLOS 1,3)