Question: Figure to accompany Table 7.1 Table 7.1 Activity Activity Time Earliest Start Earliest Finish Latest Start Latest Finish Slack A 2 0 0 2 0
Figure to accompany Table 7.1 Table 7.1
| Activity | Activity Time | Earliest Start | Earliest Finish | Latest Start | Latest Finish | Slack |
| A | 2 | 0 | 0 | 2 | 0 | |
| B | 1 | 2 | 3 | 3 | 4 | 1 |
| C | 3 | 2 | 5 | 2 | 5 | 0 |
| D | 7 | 3 | 10 | 4 | 11 | |
| E | 3 | 5 | 8 | 11 | 3 | |
| F | 5 | 11 | 5 | 11 | 0 | |
| G | 4 | 11 | 15 | 11 | 15 | 0 |
Using the information shown in Table 7.1, what is the project duration?
Group of answer choices
15
10
12
14