Question: Give the following project: Task Immediate Predecessors Time Earliest Start Earliest Finish Latest Start Latest Finish Slack A 2 0 2 0 2 B A

Give the following project:

Task

Immediate

Predecessors

Time

Earliest

Start

Earliest

Finish

Latest

Start

Latest

Finish

Slack

A

2

0

2

0

2

B

A

3

2

5

5

8

C

A

4

2

6

7

11

D

A

6

2

8

2

8

E

B,C,D

11

F

B,D

14

G

B,C,D

10

H

E,F,G

2

22

24

22

24

a. Draw the network

b. Complete the table and identify the critical path.

c. What is the impact on project duration of the following changes in task times?

Task Change

Duration Change

F increases by 3

E increases by 4

F decreases 1

F decreases by 4

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!