Question: Give the following project: Task Immediate Predecessors Time Earliest Start Earliest Finish Latest Start Latest Finish Slack A 2 0 2 0 2 B A
Give the following project:
|
Task | Immediate Predecessors |
Time | Earliest Start | Earliest Finish | Latest Start | Latest Finish |
Slack |
| A |
| 2 | 0 | 2 | 0 | 2 |
|
| B | A | 3 | 2 | 5 | 5 | 8 |
|
| C | A | 4 | 2 | 6 | 7 | 11 |
|
| D | A | 6 | 2 | 8 | 2 | 8 |
|
| E | B,C,D | 11 |
|
|
|
|
|
| F | B,D | 14 |
|
|
|
|
|
| G | B,C,D | 10 |
|
|
|
|
|
| H | E,F,G | 2 | 22 | 24 | 22 | 24 |
|
a. Draw the network
b. Complete the table and identify the critical path.
c. What is the impact on project duration of the following changes in task times?
| Task Change | Duration Change |
| F increases by 3 |
|
| E increases by 4 |
|
| F decreases 1 |
|
| F decreases by 4 |
|