Question: Fill in the table below with the three point estimate ( E ) and variance ( V ) for each task. E = a +

Fill in the table below with the three point estimate (E) and variance (V) for each task.
E=a+4m+b6
V=(ba6)2
Task
Predecessors
a
m
b
E
V
A
none
2
5
8
Answer 1 Question 1
Answer 2 Question 1
B
A
1
2
9
Answer 3 Question 1
Answer 4 Question 1
C
A
0.25
0.5
3.75
Answer 5 Question 1
Answer 6 Question 1
D
B
1
1
7
Answer 7 Question 1
Answer 8 Question 1
E
B and C
1
2
9
Answer 9 Question 1
Answer 10 Question 1
F
D and E
1
3
11
Answer 11 Question 1
Answer 12 Question 1
What is the critical path?
Multiple choice 1 Question 1
1. ABCD
2. ABDF
3. ABEF
4. ABCF
5. ACDF
4. ACEF
What is the duration of the project? Answer 13 Question 1
What is the variance of the duration of the project? Answer 14 Question 1
Suppose we are interested in calculating the probability that the project will be completed in 14 time units.
What Z value would you compute? Answer 15 Question 1
Z=XEV
(Only sum the critical path values for E and V)
what would be the probability? Answer 16 Question 1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!