Question: Fill in the table below with the three point estimate ( E ) and variance ( V ) for each task. E = a +
Fill in the table below with the three point estimate E and variance V for each task.
Eamb
Vba
Task
Predecessors
a
m
b
E
V
A
none
Answer Question
Answer Question
B
A
Answer Question
Answer Question
C
A
Answer Question
Answer Question
D
B
Answer Question
Answer Question
E
B and C
Answer Question
Answer Question
F
D and E
Answer Question
Answer Question
What is the critical path?
Multiple choice Question
ABCD
ABDF
ABEF
ABCF
ACDF
ACEF
What is the duration of the project? Answer Question
What is the variance of the duration of the project? Answer Question
Suppose we are interested in calculating the probability that the project will be completed in time units.
What Z value would you compute? Answer Question
ZXEV
Only sum the critical path values for E and V
what would be the probability? Answer Question
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
