Question: Fill in the table below with the three point estimate ( E ) and variance ( V ) for each task. What is the critical

Fill in the table below with the three point estimate (E) and variance (V) for each task.
What is the critical path?
ABCD
ABDF
ABEF
ABCF
ACDF
ACEF
 Fill in the table below with the three point estimate (E)